Step 1 Loosen the two bolts on the monitoring module, as shown by (1) in
Step 2 Open the two crowbars on the monitoring module, as shown by (2) in
Step 3 Gently pull out the monitoring board, as shown by (3) in
Figure 5-13 Replacing the monitoring board
Step 4 Install a new monitoring module.
Step 5 Close the two crowbars and tighten the two bolts on the monitoring module in turn.
----End