Locked operation
Provided that the user administration has been activated by the assignment of passwords for the different
authorization types, the controller operation is first locked after turning on the unit, recognizable by the
closed lock icon in the header.
In the locked view the controller provides all display functions. No setting functions are available.
The setpoints are shaded (light grey) in normal display. Changing them by direct entry in the fixed value
operating mode is not possible. The functional icons for setpoint entry and program start in the footer are
without function.
After turning on the unit, user log-in is required to operate the controller (chap. 12.2).
Operation without user log-in / without password-protection
If the password function has been deactivated, after turning on the unit without user log-in there are those
controller functions available, which correspond to the highest authorization level without a password
protection. There is no lock icon in the header.
9.8

Loading

Without technical ventilation the chamber must not be loaded with material containing sol-
vents.
The chamber cannot be loaded when turned off / in standby mode .
Before loading the material to be loaded, note:
When loading the chamber also in the context of intended use, an explosive mixture may form in the
working space. Therefore, a safety area of at least. 1 m in front of the oven must be considered.
• Ensure equipotential bonding. The accessible installation and operating surface of the equipment must
be conductive. This installation and operating surface must be connected with the vacuum drying oven
according to the grounding plan (Chap. 6.8).
• The personal protective equipment (PPE) of the operating personnel must be implemented ESD pro-
tected. This applies also to gloves.
• Activate the technical ventilation (extraction):
The operator shall provide active ventilation (technical ventilation according to country-specific regula-
tions (TRBS 2152 Part 2 for Germany) prior to commissioning of the chamber. It must include the en-
tire installation area of the vacuum drying oven. Loading must take place under technical ventilation in
the safety area in front of the oven.
VDL (E3.1) 06/2020
Page 95/206

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vdl 23Vdl 23-ulVdl 56Vdl 56-ulVdl 115Vdl 115-ul

Table of Contents