Huawei UPS5000-E Series User Manual page 75

Integrated ups, 50/125 kva
Hide thumbs Also See for UPS5000-E Series:
Table of Contents

Advertisement

UPS5000-E-(50 kVA-125 kVA)
User Manual (Integrated UPS 3.0)
Figure 3-10 Adjusting the leveling feet
----End
Installing the UPS on an ESD Floor
A support is required when the UPS is installed on an ESD floor. The support height depends
on the height between the ground and the ESD floor.
Step 1 Lift the cabinet onto the support and align the mounting holes on the cabinet with those on the
support.
Step 2 Level the UPS by adjusting the anchor bolts and using a level.
Step 3 Insert four M12 bolt assemblies into the mounting holes for the UPS and support. Partially
tighten the bolts.
Issue 09 (2019-12-20)
Wrench an anchor bolt clockwise to elevate a cabinet, or wrench an anchor bolt
anticlockwise to lower it. The cabinet feet can be adjusted within a range of 0–8 mm.
To prevent cabinet tilting, adjust the four anchor bolts instead of one anchor bolt.
Use a measuring tape for measurement when leveling the cabinet to ensure that the height
between the cabinet top and the ground is 2000 mm + 3 mm.
Do not remove anchor bolts. Otherwise, you need to rework them for use.
Copyright © Huawei Technologies Co., Ltd.
3 Installation
66