Figure 8-7 Removing the copper bar
Step 4 Turn off the new circuit breaker, install a new circuit breaker using an extracting kit, and
close the handle.
Figure 8-8 Closing the handle
Step 5 Reinstall the protective cover for the circuit breaker and turn on the circuit breaker. Check
that the load is operating properly.
----End

8.4 Replacing an ATS

Before the replacement, ensure that the load services are not affected or obtain written consent
from the customer.
Procedure
Step 1 Switch off the upstream power distribution circuit breaker of the UPS cabinet, and use a
multimeter to check that the ATS input terminal is not energized.
Step 2 Switch off the output and input circuit breakers in the UPS cabinet.
Step 3 Remove the protective cover.