UPS5000-E-(40 kVA-128 kVA) User Manual (Integrated UPS 2.0) Issue Date 2018-04-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
Follow the precautions and special safety instructions provided by Huawei when operating Huawei products. Huawei will not be liable for any consequences that are caused due to violations regarding general safety regulations and equipment design, production, and usage safety standards.
Page 10
Personal Requirements Only Huawei engineers or engineers certified by Huawei are allowed to perform UPS commissioning and maintenance. Otherwise, human injury or equipment damage may occur, and any resulting UPS faults will be beyond warranty scope.
Page 15
1 Safety Precautions To ensure battery safety and efficient battery management, use the batteries delivered with the UPS. Huawei shall not be responsible for battery damage caused by using non-Huawei batteries for Huawei UPSs. Ensure lead-acid battery handling is in accordance with local regulations.
Check that the fittings comply with the packing list. If some fittings are missing or do not comply with the packing list, record the information and contact your local Huawei office immediately. If the UPS installation environment is in poor condition and the UPS will be stored for a long time after it is unpacked, wrap the UPS with the original plastic coat to prevent dust.
4.1.9 Connecting Signal Cables 4.1.9.1 Connecting a Remote EPO Switch Huawei does not provide an EPO switch and cable. Prepare them before installation. The 22 AWG cable is recommended. AWG is short for American wire gauge. To prevent problems, equip the EPO switch with a protective cover, and enclose the cable with a protective tube.
6.1.2 Commissioning Context Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Turn on the circuit breakers of the ATS operation mechanism (Q1 and Q2 in the left lower part at the rear of the cabinet) to power on the ATS operation mechanism.
Page 168
User Manual (Integrated UPS 2.0) 6 Operations The UPS begins to work in normal mode and starts initialization. The LCD displays the Huawei logo and an initialization progress bar. Step 2 After the LCD starts properly, perform the following operations: ...
Page 171
High or low charging power tends to shorten the battery lifespan, or even damages batteries. If you do not know how to confirm the battery capacity, contact Huawei technical support. Number of cells refers to the number of 2 V cells in a single battery string connected to the UPS.