Commissioning
Requirements
The following requirements must be fulfilled for commissioning of the wirefeeder:
-
-
-
-
-
-
-
Commissioning -
When using a TWIN welding process, welding is started by an active welding start signal
start of welding
from the robot controls.
86
All components installed and connected in accordance with the "Installation" section
All necessary welding media connected to the wirefeeder
Feed rollers inserted into wirefeeder
Wire electrode threaded in
Contact pressure of the feed rollers set
Motor calibration carried out
All covers closed, all side pieces installed and all safety devices in good order and in-
stalled in the location intended (for example, protective covers)
Need help?
Do you have a question about the TPS/i Robotics TWIN Push and is the answer not in the manual?