6.3

Preparing commissioning

Procedure
1. Remove the transportation lock of the pressure vent valve, if applicable.
Figure 6-1
2. Check the oil level in the gearbox, and correct the oil level, if necessary. See Checking
and changing lubricants (Page 145)
Note
For gearboxes with long-term preservation and gearboxes supplied completely filled with
oil.
We recommend a complete oil change after a storage time longer than 24 months.
3. Mount an oil expansion unit. See Mount the oil expansion unit (Page 103)
You have now prepared commissioning.
6.4

Commissioning procedure

Procedure
● Ensure that the frequency converter is correctly parameterized.
● Commission the motor with an appropriate commissioning tool, e.g. "Drive ES" or
"STARTER".
● Follow the steps of the commissioning tool.
You have commissioned the motor.
Switching off
● Switch off the motor at the frequency converter.
SIMOTICS S-1FG1 servo geared motor
Operating Instructions, 07/2019, A5E47360747B AA
Transportation lock. Remove in the direction of the arrow.
Pressure vent valve with securing clip
Commissioning
6.3 Preparing commissioning
129

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents