Commissioning

5.2 Preparing for commissioning

5.2
Preparing for commissioning
Before starting commissioning, you must know the following data:
● Which motor is connected to the inverter?
Note down the Article No. of the motor and the motor's nameplate data.
If available, note down the motor code on the motor's nameplate.
● In which region of the world is the motor to be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
● How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).
Note the appropriate motor data for connecting.
5.2.1

Inverter factory setting

Motor
With its factory settings, the inverter is set up for an induction motor suitable for the power
rating of the Power Module.
Inverter control
You will find the factory setting of the inverter control in chapter: Factory settings of the
inputs and outputs (Page 50)
66
Converter with control units CU240D-2
Operating Instructions, 04/2015, FW V4.7.3, A5E34262100B AB

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics g120d cu240d-2 dpSinamics g120d cu240d-2 pn-f ppSinamics g120d cu240d-2 pn-f foSinamics g120d cu240d-2 dp-fSinamics g120d cu240d-2 pnSinamics g120d cu240d-2 pn-f

Table of Contents