15 Commissioning the control panel with MS9i
Building Technologies
Fire Safety

Commissioning the control panel with MS9i detector lines

detector lines
Prerequisites
The ↑ 'Station' is installed, but the batteries are not connected yet.
The cables for the ↑ detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
SintesoWorks is installed on the PC.
The current firmware and ↑ BDV are available on the PC.
You will find additional information about the individual steps on the specified
pages.
Commissioning steps
1. Create the ↑ pre-configuration of the MS9i detector line. You will find more
information in document 009078. See chapter 'Applicable documents'.
2. Prepare the ↑ 'Station' for commissioning – without ↑ BDV installation.
Link [➙ 77]
3. Connect the PC to the 'Station'. Link [➙ 27]
4. Load the configuration from the PC to the 'Station'. Link [➙ 30]
5. Test the function of the 'Site'. Link [➙ 91]
6. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [➙ 30]
7. Disconnect the PC from the 'Station'. Link [➙ 27]
8. Perform the completion tasks. Link [➙ 91]