Commissioning overview
5
Commissioning variants
5 Commissioning overview
5.1 Commissioning variants
Without
No pre-
SintesoWorks
configuration
possible
With
Without pre-
SintesoWorks
configuration
With pre-
configuration
34 | 188
Building Technologies
Fire Safety
The ↑ 'Stations' on the FCnet, such as control panels FC2020/FC2040 and fire
terminals FT2040 and FT2080, are connected to the power supply and
commissioned by the installation and commissioning personnel.
●
Networked 'Stations' must only be commissioned with SintesoWorks.
●
Standalone control panels can be commissioned with or without SintesoWorks.
NOTICE
Impermissible commissioning procedures result in faults during operation.
●
Only the procedures described in this document are permitted.
In order to satisfy Ordinance No. 305/2011 (the Construction Products Regulation –
CPR), the firmware of a newly installed fire detection installation must be current
market package version MP6 or higher.
NOTICE
Firmware version of a newly installed fire detection installation not updated
No CPR conformity
●
Compare the firmware version of a newly installed fire detection installation
with the firmware version MP6.
●
Update the firmware if necessary.
The table below provides an overview of the procedure for commissioning the
'Stations'. The letters A, B1, B2 and C refer to the detailed descriptions in the
following chapters.
Standalone control panel
A
●
Auto-configuration
●
Adaptations on the ↑ Person
Machine Interface
B1
●
Auto-configuration
●
Adaptations in SintesoWorks
B2
●
Read in the FDnet devices by line
●
Assign the logical elements to
SintesoWorks
Table 1: Commissioning variants
Networked 'Stations'
Not possible.
C
●
Initialize the 'Stations' for
networking
●
Read in the FDnet devices by line
●
Assign the logical elements to
SintesoWorks
009052_s_en_--
2016-06-02