B2 - Commissioning standalone 'Station' with PC, with pre-configuration
8
8 B2 - Commissioning standalone 'Station' with
42 | 188
Building Technologies
Fire Safety
PC, with pre-configuration
The procedure in this chapter is only valid for FDnet detector lines.
In this commissioning variant, in SintesoWorks, first manually configure a ↑ 'Site'
up to 'Line' level. Then read in the FDnet devices and adapt the configuration
manually in SintesoWorks.
Prerequisites
●
The ↑ detector lines and FDnet devices are installed.
●
The acceptance test has been carried out for the detector lines.
●
The ↑ 'Station' is installed, but the batteries are not connected yet.
●
The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not yet connected.
●
SintesoWorks is installed on the PC.
●
The current firmware and ↑ BDV are available on the PC.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. In SintesoWorks create a ↑ 'Site' and configure it manually up to 'Zone' level.
2. Prepare the ↑ 'Station' for commissioning – without ↑ BDV installation.
Link [➙ 77]
3. Connect the PC to the 'Station'. Link [➙ 27]
4. Load the configuration from the PC to the 'Station'. Link [➙ 30]
5. Read-in the FDnet devices. Link [➙ 85]
6. Load the configuration from the 'Station' to the PC. Link [➙ 32]
7. Adapt the configuration in SintesoWorks. Link [➙ 80]
8. Load the configuration from the PC to the 'Station'. Link [➙ 30]
9. Test the function of the 'Site'. Link [➙ 91]
10. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [➙ 30]
11. Disconnect the PC from the 'Station'. Link [➙ 27]
12. Perform the completion tasks. Link [➙ 91]