Instructions; Enc82 Carrier Gas Bottle Rack Installation; Materials; Figure 3-35 Carrier/Calibration Gas Bottle Rack Installation - ABB NGC8206 User Manual

Chromatograph
Hide thumbs Also See for NGC8206:
Table of Contents

Advertisement

3.17.1 Instructions

1) Position the bottle rack in close proximity to the NGC.
2) Secure the rack to the pipe meter run with the provided mounting hardware.
3) Install both the carrier and calibration gas bottles in the rack.
4) Strap both bottles in the rack to prevent falling.

Figure 3-35 Carrier/Calibration Gas Bottle Rack Installation

3.18 ENC82 Carrier Gas Bottle Rack Installation

3.18.1 Materials

1 ea. bracket with chain assembly attached
2 ea. 3/8"-16 x 5/8 SST hex head bolt
2 ea. 3/8" SST split washers
2 ea. 3/8" SST flat washers
3.18.2 Instructions
1) Locate bracket holes on the rear of the large enclosure or the side of the
2) Place a split washer then a flat washer on one of the 5/8" bolts and insert through
bolt hole located in the bottle rack bracket into the corresponding hole located
along the bottom edge of the enclosure, then tighten (see
2101510 Rev. AG
CARRIER
GAS
TO NGC
The carrier gas bottle rack is installed on the back of the
ENC82L or the side of the ENC82S.
A gas regulator should be installed on each gas bottle (see
Figure
small enclosure stand.
CALIBRATION
GAS
3-36).
Figure
3-37).
Page 3–35