Emc-Compliant Cable Routing On The Plant Side On Cable Racks And In Cable Ducts - Siemens SINAMICS G130 Engineering Manual

Sinamics - low voltage sinamics drives
Hide thumbs Also See for SINAMICS G130:
Table of Contents

Advertisement

EMC Installation Guideline
Engineering Information
2.4.7.3

EMC-compliant cable routing on the plant side on cable racks and in cable ducts

1)
When single-wire cables (e.g. unshielded supply connection cables) are used in three-phase systems, the three
phase conductors (L1, L2, and L3) must be bundled as symmetrically as possible to minimize the magnetic leakage
fields. This is particularly important when several single-wire cables need to be routed in parallel for each phase of a
three-phase system due to high amperages. The illustration below uses an example of a three-phase system with
three single-wire cables per phase routed in parallel (with and without PE conductor).
a) Three parallel single-wire cables per phase with PE conductor
b) Three parallel single-wire cables per phase without PE conductor
If the preferred two-layer bundle arrangement illustrated above is not feasible for mechanical reasons with special
applications– for example, where trailing cables are used – then the cables must be bundled in one layer in a single
plane as illustrated in the diagram below.
a) Three parallel single-wire cables per phase with PE conductor in a single plane
b) Three parallel single-wire cables per phase without PE conductor in a single plane
2)
3)
and
: See following page for explanations
SINAMICS Engineering Manual – November 2015
247/528
Ó Siemens AG

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics g150Sinamics s120Sinamics s150

Table of Contents