Chapter Nine Server Installation Guide

The server can be converted to rack-mounted server. If your server is rack-mount-
ed configuration, please refer to this chapter.
The Guide will help you to understand how to install Inspur Yingxin NP5540M3
server in Inspur server cabinet or compatible standard industrial cabinet.

9.1 Cabinet Preparation

Angle rail adjustment: in order to guarantee the server can be installed in the cabi-
net normally, the clearance between the front and rear part of the angle rail should be
adjusted to be at least larger than 650mm; inner width between left angle rail and right
angle rail should be larger that 480mm, the space between cabinet door and front angle
rail larger than 60mm.
Leveling cabinet: the cabinet must be installed in a stable place. Adjust the four
support feet at the bottom of the cabinet to make the cabinet stable on the ground.
Meanwhile, dismount the cabinet door for convenience of guide rail installation.
Cabinet grounding: to avoid electric shock, a grounding device must be installed
in the cabinet. If the server power line is installed in the power socket, which consti-
tutes a portion of the cabinet, grounding should be properly provided for the cabinet. If
the server power line is inserted into the power socket in the wall, the grounding device
in the power socket just provides grounding for the server, and then proper grounding
protection for cabinet and other internal devices should be provided. We recommend
you to use the cabinet specially designed by Inspur for the server. If so, the internal of
the cabinet should be already grounded. Please don't change the ground joint in the
cabinet unless it is of absolute necessity.
Temperature: if installed in the cabinet, the operation and working temperature of
the server can't be lower than 5 ℃ and higher than 35 ℃ .
Ventilation: the cabinet used by server cluster must provide enough wind cur-
rent for the front of the server to ventilate, and must ensure 4100Btu heat discharge
per hour. The cabinet selected by the cluster and ventilation condition must correspond
with requirements of the server.
Front and back angle rail spacing: before the rails installation, please adjust the
68