8.2.3 Procedure for initial start-up

► By switching on the main switch Q1, the components installed in the cabinet system
76
are supplied with voltage.
The 24 V DC voltage of the cabinet system supplies the control boards externally
with voltage. This makes it possible to parameterize the control boards in advance
without supplying the drive converter with power.
The communication with the converters can be established via the Ethernet connec-
tion in the cabinet door as well as the diagnostic interfaces on the control boards.
This requires a PC and the appropriate software to parameterize the converters.
The structure of the communication is described in the application manuals of the
control boards.
The IP address for the parameterization via the control is 192.168.0.100.
Information on the F5 control boards can be found here.
00f5gebk320.pdf
Information on the F6 control boards can be found here.
00f6nesk000.pdf
The WRA (AFE) is pre-parameterized ex works via a download. No further settings
need to be made.
Adjustments must only be made if the cabinet system is not operated at 690 V AC
voltage.Information can be found in the programming manual AFE housing V.
Instructions for programming can be found here.
Programming instructions AFE