Switching on and preparing for commissioning

Carrying out of repairs
Anywhere in the automation equipment where faults might cause physical injury or major
material damage, in other words, where faults could be dangerous, additional external pre-
cautions must be taken, or facilities must be provided, that guarantee or enforce a safe
operational state, even when there is a fault (e.g. using an independent limit value switch,
mechanical locking mechanisms, EMERGENCY STOP/EMERGENCY OFF devices).
4.1

Switching on controller

Before switching on
Make sure that:
● You have finished the mechanical installation of the whole system based on the
information included in the chapter "Mounting (Page 13)" or the
Manual
● You have completed the wirings of the whole system according to the information
included in the chapter "Connecting (Page 19)" (if you use the default PLC program) or
the
Switching on
Do as follows:
1. Power on the mains supply.
2. When the NC enters the main screen, check the NC normal status according to the status
LEDs on the PPU.
POK: green
RDY: green
TEMP: unlit
For detailed information about the status LEDs, refer to the section "Status LEDs
(Page 32)".
3. Check the drive normal status:
– "S-run" is displayed.
– LED "RDY/JOG": green
– LED "ERR": dark
For detailed information about the SINAMICS V60 drives, refer to the
Getting Started
Commissioning Manual
Commissioning Manual, 01/2015, 6FC5397-4EP10-0BA0
DANGER
.
Electrical Installation Manual
.
.
4
Mechanical Installation
SINAMICS V60
29

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents