2. Condensate Piping for Multiple Boilers

The number of condensate treatment tanks required for multiple
boiler installations depends on the total amount of condensate
produced by the system. As a general rule, CB recommends one
tank per 5-6 million BTU/hr of total boiler capacity. Model CFC
capacities are as follows:
CFC Model
BTU/hr
3300
3,300,000
2500
2,500,000
1800
1,800,000
1500
1,500,000
1000
1,000,000
750
750,000
500
500,000
See Figure 2-36 and Figure 2-37 for suggested piping. A drain trap
is built into the condensate tank. Make-up water must be supplied
at the connection shown in order to prevent flue gas from entering
an idle boiler. An internal float in the condensate tank activates the
make-up water valve.
Part No. 750-263
Max.
Max. Boilers
Condensation
per Tank
GPH
22
2
17
2
12
3
9
4
7
5
5
8
3.5
8