28.Attach front skirt panel to the side panels.
29.Install front panel.*
*Size 3300 front panel is 2 pieces.
Assembly is now complete.
B. FLUE GAS / COMBUSTION AIR CONNECTIONS
The flue gases from the Model CFC boiler should be removed via a
gas-tight, temperature and corrosion resistant flue gas pipeline.
Only flue gas systems approved and tested by the relevant region or
Figure 2-17
Figure 2-18
Part No. 750-263