Pre-installation: at the site

Before beginning the installation, verify that you have all the equipment on site by comparing
the list of items ordered against the items in the boxes. Your project manager can supply you
with an inventory list. Do not rely solely on the packing slips inside the boxes.
The pre-installation team should have done the following tasks. If they were not all done, do not
continue with the installation.
Verify that the open, customer-supplied, EIA-310D (or equivalent) standard 19-in. (48-cm)
4-post equipment rack(s) is(are) properly installed and solidly secured. Make sure that the
screws that come with the racks are there. If using a rack cabinet, make sure it has
adequate ventilation.
Verify that the rail kit to support the media server is available for installation.
Verify that the rail kit, required to support the very heavy UPS, is installed on the rack or
available for installation. For information on installing the rails, see the documentation that
comes with the rail kit.
Verify that the equipment rack(s) is(are) grounded per local code. See Job Aid: Approved
Grounds (555-245-772).
Verify that the customer provides AC power to the rack from a nonswitched outlet.
Verify that cabling for theTN2312BP (IPSI) circuit packs is labeled and runs from the
control hardware rack to the port networks or that appropriate connectivity is provided.
Installing and Configuring the Avaya S8500 Media Server
Pre-installation: at the site
February 2006
13