Flatbed / Icc Card Nvram; Rip Board/Operator Panel Replacement; Printhead Controller Board / Engine Board Replacement - Lexmark X925 Service Manual

Hide thumbs Also See for X925:
Table of Contents

Advertisement

7541-03x

Flatbed / ICC card NVRAM

The flatbed ICC card contains NVRAM. Do not use an ICC card from another X925 printer. Using an ICC card or
complete flatbed assembly from another machine will result in a 950.10 NVRAM mismatch error.

RIP board/operator panel replacement

This procedure should only be followed if both the RIP board and operator panel fail. If you only need to replace
one of the FRUs follow the startup procedure described in the FRU's removal procedure.
CAUTION - POTENTIAL INJURY: There is danger of explosion if a lithium battery is incorrectly
replaced. Replace it only with the same or an equivalent type of lithium battery. Do not recharge,
disassemble, or incinerate a lithium battery. Discard used batteries according to the manufacturer's
instructions and local regulations.
Warning: If the operator panel and the RIP board are being replaced at the same time, replace the parts in this
order to avoid damage to the machine.
1.
Replace the RIP card first. Note: Do not replace the new operator panel and RIP card in the machine at the
same time.
2.
After installing the new RIP card, and before installing the new operator panel, start the printer into
diagnostics mode.
3.
After the printer has completed startup, turn off the printer and replace the operator panel.
Note: Note: If the operator panel display has failed, the printers' startup cycle is complete when the driver
motor and fans shut down, and the machine is quiet.
4.
After installing the new operator panel, start the printer in to diagnostics mode, and allow the printer to go
through a complete startup cycle and the display to go to Ready.
5.
If the problems persist, leave the new operator panel in the machine, place the old RIP card back in the
machine, and start it up. After the machine startup, shut down the machine, and install the new RIP card.
After installing the new RIP card, restart the machine, and let it go through the startup cycle.
After this procedure is completed successfully, there is no need to adjust any settings.
If the above procedure fails, you must contact the technical support center for further instructions.

Printhead controller board / engine board replacement

This procedure should only be followed if both the printhead controller board and engine board are being
replaced. If you only need to replace one of the FRUs follow the startup procedure described in the FRU's
removal procedure.
Warning: If the printhead controller board and the engine board are being replaced at the same time, replace
the parts in this order to avoid damage to the machine.
1.
Replace the printhead controller board first. Do not replace the printhead controller board and engine
board in the machine at the same time.
2.
After installing the new RIP card, and before installing the new operator panel, start the printer.
3.
After the printer has completed startup, turn off the printer and replace the operator panel.
Note: If the operator panel display has failed, the printers' startup cycle is complete when the driver motor
and fans shut down, and the machine is quiet.
4.
After installing the new operator panel, start the printer, and allow the printer to go through a complete
startup cycle and the display to go to Ready.
5.
If the problems persist, leave the new operator panel in the machine, place the old RIP card back in the
machine, and start it up. After the machine startup, shut down the machine, and install the new RIP card.
After installing the new RIP card, restart the machine, and let it go through the startup cycle.
After this procedure is completed successfully, there is no need to adjust any settings.
4-2