Separate safety earth terminals are located at the back of the power distribution unit.
•
Keep the ground wire in the laser rack connected.
•
Ensure that all AC power connections comply with local and national electrical codes.
The electrical installation is subject to the approval of all local authorities having jurisdiction.
Number of laser
modules
2
3
4
5
6
7
8
9
10
11
12
Four circuits is the preferred configuration. If you install fewer circuits, remove the rectifiers
that are not connected to the AC power. Rectifiers not connect to AC power emit an audible
signal.
Projector power requirements
•
One (100 - 240) VAC, 10 A, (50 - 60) Hz wall outlet.
D4KLH60/Mirage 4KLH Installation Guide
020-101374-01 Rev. 1 (05-2014)
2000 W Rectifiers
Required for N + 1
Redundancy
3
3
4
4
5
5
6
6
7
7
8
Number of (200 -
240) VAC, 30 A
Circuits Required
2
2
2
2
3
3
3
3
4
4
4
Installation
26