Single Commissioning

Overview
For single commissioning, you set the parameter of the inverter manually. You use BOP
(Basic Operator Panel) or STARTER (Commissioning software via PC) for commissioning.
Note
We recommend commissioning via STARTER. The commissioning process using STARTER
is driven by dialog boxes and will not be interpreted in this manual. This manual describes
the parameter related commissioning via BOP.
Settings of commissioning
Commissioning the G120 inverter comprises different settings and kinds of single
commissioning. The following list provides you an overview:
● Basic commissioning
● Further settings for commissioning
For detailed information to the settings of single commissioning, refer to the section
"Commissioning with BOP".
Factory settings
The inverter is delivered with identical factory settings for all CU240S Control Units; except
the following settings:
● Command source
● Setpoint source
● Values depending on the Power Module
For details to the factory settings, refer to the Parameter Manual.
Note
After the first power on, the fault F0395 will appear. This means, no commission is until now
implemented. After confirming the message, you can proceed commissioning.
Control Units CU240S
Operating Instructions, 07/2008 - FW 3.2, A5E00766042B AD
– Quick commissioning
– Motor data identification
– Speed control optimization
– Calculating the motor/control data
– Commissioning the application
– Reset parameters to factory settings
– Commissioning the fail-safe functions (only in fail-safe applications)
The factory settings of the Power Modules are specific for the type of PM.
Commissioning
5.1 Single Commissioning
47

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents