Server Handling Precautions

Caution – Deploy the antitilt bar on the equipment rack before beginning an
installation.
Caution – The SPARC Enterprise T5220 server weighs approximately 55 lb (25. kg).
Two people are required to lift and mount this 2U server into a rack enclosure when
using the procedures in this document.
Caution – When completing a two-person procedure, always communicate your
intentions clearly before, during, and after each step to minimize confusion.
Related Information
"Input Power Information and Precautions" on page 4
Sun SPARC Enterprise T5120 and T5220 Servers Documentation
SPARC Enterprise T5120 Server Getting Started Guide
SPARC Enterprise T5220 Server Getting Started Guide
SPARC Enterprise T5120 Server Getting Started Guide (DC)
SPARC Enterprise T5220 Server Getting Started Guide (DC)
Preparing for Installation
3

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SPARC T5120 and is the answer not in the manual?

This manual is also suitable for:

T5220

Table of Contents