Replacing the BlackDiamond 10808 Switch Fan Tray, Air Filter, and Power Supply Controller

Installing a Power Supply Controller

NOTE
The power supply controllers are hot-swappable. You do not need to turn off power to a BlackDiamond 10808 switch
to install a power supply controller.
To install a power supply controller:
1 Attach the ESD-preventive wrist strap to your wrist and connect the metal end to the ground
receptacle on the top left corner of the BlackDiamond chassis front panel.
2 If a blank faceplate is covering the power supply controller bay, remove it and save it for future use.
3 Verify that the power supply controller is right side up.
4 Slide the power supply controller into the slot, aligning the notch on the top of the slot with the
power supply controller.
5 Tighten the captive thumbscrews to secure the power supply controller into the slot.

Verifying a Successful Installation

After you supply power to the switch, the switch performs a power-on self test (POST).
During the power-on self test:
All ports are temporarily disabled.
The packet LED is off.
The power LED is on.
The MGMT LED flashes until the switch successfully passes the POST.
If the switch passes the POST, the MGMT LED blinks at a slow rate (one blink per second). If the switch
fails the POST, the MGMT LED shows a solid yellow light.