Preparing the Cables

Three spade-type terminals are provided with the PSU. You need a crimping tool to attach the terminals
to the power and ground cables.
To prepare the cables:
1 On each wire, strip 0.25 inch of insulation from one end.
2 Insert the stripped wire end all the way into the barrel of the terminal
terminal securely to the wire.
Figure 157: Attaching a Terminal to a Cable

Installing the Power Supply

To install a Summit X480 DC PSU:
1 Attach an ESD-preventive wrist strap to your bare wrist and connect the metal end to an appropriate
ground point on the rack.
2 If necessary, remove a blank panel from the back of the Summit X480 series switch
Figure 158: Removing a Blank Panel
3 Verify that the PSU is right side up (see
4 Carefully slide the PSU all the way into the power supply bay (see
the latch snaps into place.
Summit Family Switches Hardware Installation Guide
SH_109
SH_157
Figure
159).
(Figure
157) and crimp the
(Figure
Figure
159). Push the PSU in until
197
158).