2.
Locate the AC power cords.
IMPORTANT:
Equally distribute the current between the PDMs.
3.
Connect a black power cable to the left power supply of each enclosure and into a PDM mounted
on the left vertical post
4.
Connect a gray power cable to the right power supply of each enclosure and into a PDM mounted
on the right vertical post.
Installing VLS9000 Cables
To install VLS9000 cables, follow the instructions in the order of the sections presented below.
Cabling the Nodes
Figure 16 Nodes port cabling
.
Item
Description
1
FC host port, port 1
2
FC host port, port 2
3
FC storage port, port 3, on primary node connects to port 0 of Fibre Channel switch #1
4
FC storage port, port 4, on primary node connects to port 0 of Fibre Channel switch #2
5
USB connector, on primary node connects to USB/Ethernet adapter, then to port 1 of switch 2510 24
6
Serial connector to access CLI
7
Video connector
8
Keyboard connector
9
NIC 1, on primary node only connects to the customer-provided external network
10
NIC 2, on primary node connects to port 1 of switch 2810 24G
11
Power supply 1
12
Power supply 2
58
Hardware Installation
Need help?
Do you have a question about the StorageWorks 9000 - Virtual Library System and is the answer not in the manual?