Installation and commissioning flowchart

Identify the frame size of your drive: R5 or R6.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection,
compatibility of the motor, motor connection,
and other technical data.
Select the cables.
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
If the drive is about to be connected to an IT
(ungrounded) system, make sure that the drive is
does not have EMC filtering intended for
grounded systems, or disconnect the EMC filter
capacitors.
Check the installation site.
Install the drive on a wall or in a cabinet.
Route the cables.
Task
Introduction to this manual 19
IEC data
(page 119) or
NEMA data
Technical data
(page 119)
Planning the electrical installation
For compliance with the European Union EMC
Directive, see
CE marking
Option manual (if optional equipment is included)
Unpacking the unit
(page 35)
If the converter was non-operational for more
than one year, the converter DC link capacitors
need to be reformed, see
Type code
(page 33)
IT (ungrounded) systems
Before installation
(page 38)
Technical data
(page 119)
Mechanical installation
Routing the cables
(page 67)
For compliance with the European Union EMC
Directive, see
CE marking
See
(page 125)
(page 45)
(page 132)
Capacitors
(page 116).
(page 70)
(page 35)
(page 132)

Advertisement

Table of Contents
loading

This manual is also suitable for:

Acs800-u31

Table of Contents