Activate the generator by pressing Space.
16.
The generator is now delivering RF energy; follow the warnings/precautions at the
17.
start of this section. Record the current being delivered to the load.
At the Check Output Curve>> prompt, using a modified LigaSure cable, connect a 30
18.
and a True RMS Meter/Current transformer to verify that the measured output is
within specification.
Activate the generator by pressing Space.
19.
The generator is now delivering RF energy; follow the warnings/precautions at the
20.
start of this section. Record the current being delivered to the load.
At the Check Output Curve>> prompt, using a modified LigaSure cable, connect a 50
21.
and a True RMS Meter/Current transformer to verify that the measured output is
within specification.
Activate the generator by pressing Space.
22.
The generator is now delivering RF energy; follow the warnings/precautions at the
23.
start of this section. Record the current being delivered to the load.
At the Check Output Curve>> prompt, using a modified LigaSure cable, connect a
24.
200
and a True RMS Meter/Current transformer to verify that the measured output
is within specification
Activate the generator by pressing Space.
25.
The generator is now delivering RF energy; follow the warnings/precautions at the
26.
start of this section. Record the current being delivered to the load.
At the Check Output Curve>> prompt, using a modified LigaSure cable, connect a
27.
500
and a True RMS Meter/Current transformer to verify that the measured output
is within specification.
Activate the generator by pressing Space.
28.
The generator is now delivering RF energy; follow the warnings/precautions at the
29.
start of this section. Record the current being delivered to the load.
At the Check Output Curve>> prompt, using a modified LigaSure cable, connect a
30.
1000
and a True RMS Meter/Current transformer to verify that the measured
output is within specification.
Activate the generator by pressing Space.
31.
The generator is now delivering RF energy; follow the warnings/precautions at the
32.
start of this section. Record the current being delivered to the load.
Record the power curve data in the data sheet provided.
33.
The Power Curve check is complete.
34.
Valleylab LS10, LS Series Single Channel Vessel Sealing Generator Service Manual
Optional Service Applications
3-17