Commissioning the system

Prerequisites

Prior to commissioning the system, check to ensure that the following prereq-
uisites are met:
• You are familiar with the different operating elements and operating levels
of the central apartment unit.
• All system components are correctly installed.
• Mains-powered components are connected to power.
• New batteries are ready to be inserted in the battery-powered devices *.
• Wired devices are connected to the KNX TP1 data bus.
• Meters are integrated correctly and connected to the consumption data in-
terface WRI982.
* To extend battery life, insert the batteries only prior to connecting the
device to the central apartment unit (for procedures, see the mount-
ing instructions of the associated device).

Procedure

Commission the system in steps:
1.
Commission the meters (if available):
2.
Enter the basic configuration for the central apartment unit.
3.
Enter extra configurations for the central apartment unit.
4.
Switch on and connect the devices communicating via radio (KNX RF).
5.
Test the wiring.
6.
Configure the wired bus communication (KNX TP1).
7.
Set the central apartment unit parameters.
Basic configuration of the central apartment
unit
You must first enter the basic configuration at the central apartment unit to
connect devices.

Switch on the central apartment unit

The central apartment unit must be switched on to enter the basic configura-
tion.
18 / 134
Siemens
Building Technologies
Synco™ living
Commissioning the system
CE1C2740en
13.12.2010

Advertisement

Table of Contents
loading

Table of Contents