Section 6
Local HMI engineering
1.
Make a sketch how to present the single line diagram.
2.
Place the apparatus, transformer and other symbols that are needed for the single line
diagram into the raster boxes.
3.
Add connection points where needed.
4.
Link the apparatus symbols with line elements.
5.
Adjust the text symbols while writing to north, east, south or west. Use the object property
window to do it.
6.
Place measurements when needed.
7.
Edit the name, unit and number of decimals of the measurements.
8.
Select each object that has a dynamic link and do the link to the corresponding process
object, see
9.
Check to select the correct function block. Function blocks of the same type can have
different instance numbers.
10. Validate that all links are done.
11. Save the complete picture.
12. Repeat the steps for all pages when more than one is needed.
13. Write to IED.
IEC09000666 V1 EN-US
Figure 56: GDE: Establish a dynamic object link
Linking process objects
To describe a process object within an IED it needs to be established in the application
configuration, configured when given with its parameters by PST and linked to be displayed in the
HMI.
Three tools are involved for the described steps:
ACT to program the application function block for apparatus and/or measurements.
PST to adapt the settings and/or configuration parameter of the application function block.
GDE to establish the link for updating the selected data attribute in the HMI of the application
function block.
The following application function blocks are used to deliver the needed information:
74
Figure
56.
© Copyright 2011 ABB. All rights reserved
1MRK 511 245-UUS A
IEC09000666-1-en.vsd
650 series
Engineering manual

Advertisement

Table of Contents
loading

Table of Contents