2.3 Mounting Procedure
1. Remove the two screws under the mounting bracket to separate it from the cabinet.
2. Mark the desired mounting height.
3. Mount the bracket on the pole as illustrated in Figure 2-2, making sure it is firmly
secured.
For Hose Clamp Rings:
a. Orient the I-shaped mounting bracket to the top hanging hole.
b. Push the mounting bracket firmly against the pole.
c. Run the hose clamp around the pole and through the two hose clamp rings on the bracket
and fasten tightly (first at the top and then the bottom).
For Threaded Rods:
a. Assemble four threaded rods into the I-shaped mounting bracket with nuts and washers.
b. Orient the mounting bracket to the top hanging hole (using caution to avoid injury).
c. Push the mounting bracket firmly against the pole.
d. Fasten the bracket to the two holding bars with four M12 screws and eight washers
until tight.
4. Install the two hoist rings to the top of the system, making sure they are securely
fastened.
5. Raise the system with the two hoist rings to the designated height (avoid scratching or
casing damage to the surface paint).
6. Hook the system on the bracket as illustrated in Figure 2-3
7. Secure the cabinet to the bracket with the two screws removed from under the mounting
bracket.
Important: if the surface coating is scratched or scraped off during transport or installation,
the damaged surface must be touched up with appropriate external-use paint.