Do not topple the system while in transport or storage.
Please keep children away from the system.

2.2 Preparing for Setup

Pole Mounting Requirements

Manpower: Two people. Weight of system is 46kg (101lbs.)
Tools:
Adjustable wrench with diameter 3/4 (19mm)
Phillips and flathead screwdrivers
Measuring tape
Surge protection devices (SPD)
Outdoor shielded dual-conductor cable (12 AWG)
Outdoor grounding wire (6 AWG)
Marking pen
316L stainless hose clamp, 15mm or wider (optional)

System Precautions

Review the electrical and general safety precautions in Appendix B.
When not servicing, always keep all covers/panels on the server closed. These must be
in place to allow for proper airflow and to prevent overheating.
Keep a one-foot (30cm) clearance from the ground to provide sufficient airflow for cabinet
cooling.
Only install the system on a pole with a diameter of between 5" and 10".
Ensure that the pole is capable to withstand the weight of the system before installation.
Various pole types and materials are regulated in different regions, please refer to local
regulations before mounting the system on a pole.
Keep a four-foot (122cm) clearance around the pole to provide operating space.
Use only the designed components and fasteners; using alternative components will invoke
unpredictable risk.
If surface paint becomes scratched or chipped off, touch it up with outdoor-use paint
18