Installation overview
Installation of a server requires the following steps:
Procedure
1. Installing the chassis into the rack.
2. Install any server options.
3. Install the operating system.
4. Install system software.
5. Register the server.
Installing the chassis into the rack
CAUTION: Always plan the rack installation so that the heaviest item is on the bottom of the rack. Install the
heaviest item first, and continue to populate the rack from the bottom to the top.
Prerequisites
Before installing the chassis, observe all necessary warnings and cautions.
Procedure
1. Unpack the system and remove all components from the chassis.
2. Install the chassis into the rack. For more information, see the installation instructions that ship with the selected rail
system.
3. Install options in the chassis.
4. Install all components in their original locations in the chassis.