4.1.3 Extra anchoring on top
The extra wall anchoring can be mounted after connecting all the stanchions to the guide.
The correct assembly order is as follows:
Bring the guide to the wall (make sure
it is in the correct position)
With a pencil mark the two ends of the
stanchion on the wall
Take the guide away from the wall
Remove the stanchion from its register
Position the stanchion next to the wall
using the previously obtained
references
Mark the drilling points
Drill a hole for the screw anchor
Fix the stanchion to the wall
Remount the register onto the
stanchion (the guide is already in the
correct position)
Tip: you can also insert the stanchion into the register from the front: position the special nuts with
their long side upright and then bring the guide to the stanchion with force.
Tip: if the wall is a long way from the guide, a threaded bar can be used instead of a screw anchor.