To connect the adapter cable to SPECTANO 100:
1. Connect the standard triaxial cable according to the color code to the SPECTANO 100 OUTPUT
and INPUT connectors.
2. Connect the adapter cables with the corresponding color code to the standard triaxial
cable.
9.4.1

Typical setup for a test cell with guard ring

DANGER
Death or severe injury caused by high voltage or current
► Do not touch the OUTPUT connector when the red LED is on or blinks.
► Always ensure that no dangerous voltages are present at any touchable
part of the device, test cell or sample.
► Do not touch the output if the guard (inner shield of the triaxial connection)
is identical with the ground (outer shield of the triaxial connection).
*
same potential
Figure 9-4
NOTICE
The safe area is only safe if the delivered cables and adapters are used.
Otherwise, this can also be a danger zone.
30
Inner conductor
Outer (ground) &
inner (guard) shield
*
Connecting SPECTANO 100 to a test cell with guard ring
Outer (ground) &
inner (guard) shield
*
Inner conductor
Barrier
Guard ring
Electrodes