11.6
Installation of coordination unit on Fire Door installations
Mount the rotor (parts 1 to 4 below) before the motor is installed on the back plate. Install the
control unit when the installation of the coordination unit is completed.
If the coordination unit will be installed on an existing installation it is possible to move the control
unit a little bit to be able to reach the motor unit during installation.
Link rod length = Cover length (CL) - 1064 mm
a Loosen the screws (1) and remove the clutch cap (2) from the rotor (3).
b Turn the clutch cap (2) depending on PULL or PUSH installation. PULL visible for PULL-installation
and PUSH visible for PUSH-installation.
c Fasten the screws (1).
d Remove plastic cover. Mount the rotor (3) on the motor unit (6) with the screw (4) and washer
(5) on the master drive unit = for the door that opens first and closes last.
5
4
1007913-EI-9.0
3
2
6
3
Issue 2014-10-28
11 Mechanical installation
1
51