After installation according to the checklist proceed as following:
1 Prepare reagents. See
2 Insert suction lances
3 Lock the occlusion frames of the peristaltic pump.
 The peristaltic pump is ready.
4 Turn on sample flow and wait until the flow cell is completely
filled.See
Establish Sample Flow, p. 30
5 Switch on power.
6 Fill system. See
7 Let the instrument run continuously for 1 hour.
Refill or replace Reagents, p. 38
A
B
C
D
Fill or Flush Reagent System, p. 31
A
Turn to lock
B
Occlusion frame
C
Rotor
D
Pump tube