Commissioning
The initial commissioning (trial run) of the battery storage system is performed by
INTILION GmbH or by personnel trained by INTILION GmbH under the supervision of the
system manager,
The system manager must have completed an INTILION scalebloc product training
session and briefing.
Following initial commissioning, the "System management" document must be signed in
duplicate. One copy is kept by INTILION GmbH and the second copy is stored in the
battery storage system.
For re-commissionings, contact INTILION GmbH (see Section "1.5 Service/customer
service").
WARNING
Make sure that you are sufficiently familiar with
The operating and control elements of the battery storage system
The equipment of the battery storage system
The way in which the battery storage system works
The immediate vicinity of the battery storage system
The safety devices in the battery storage system
The procedure to follow in an emergency
INTILION scalebloc 0.5C
Risk of injury due to lack of space!
When commissioning the battery storage system, there is a risk of injury
such as scratches, puncture wounds or fractures as a result of an
excessively close arrangement of the necessary work equipment and/or
components.
Cordon off the danger zone.
Keep unauthorised persons away from the area.
Appoint a responsible person.
77