5.3

Preparatory measures

Before installing the battery storage system, it must be ensured that
The foundation has been prepared in line with the specifications
The connections on the AC-distribution side have been prepared
The necessary installation tools are available
5.4

Disassembling the transport pallet

The battery storage system is delivered on a transport pallet. The fixing screws
must be removed prior to unloading.

Illustration 11: Disassembling the transport pallet - removing the fixing screws

Remove the fixing screw (1) at each corner.