10 Decommissioning and disassembly
10.2 Disassembly
10.2.2.9

Preparing the battery storage system for loading

Remove the fastenings securing the battery storage system onto the foundation.
Follow these steps in reverse order to secure the floor plates.
Insert the side panels and push them backwards to the back of the battery storage
system.
Secure the side panels using the previously removed screws.

Illustration 69: Securing the front panel

Insert the front panel and push it as far as it will go (approx. 10 mm) in the direction of
the arrow.
Secure the front panel using the previously removed screws (1).
Close the doors of the battery storage system.
To this end, start by lifting up the respective latching hook.