Installation; Unpacking; Ups Clearance - Toshiba 4400 Series Installation And Operation Manual

Three phase - 15/20/25/30/50/80/100 kva
Table of Contents

Advertisement

8

Installation

8.1

Unpacking

Unpack the UPS indoors on a paved floor. The UPS should be as close as possible to its final storage location. Allow enough
space for forklift operations to unpack the UPS crate. Then remove the crate.
Points to observe
Retain all small articles during unpacking and installation.
Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.
DO NOT damage the UPS when using tools to remove packaging materials.
If provided, DO NOT remove the plastic sheet cover, until installation.
Do not remove the fan covers until UPS start up. The fan covers should be removed by factory authorized
personnel. Packing materials should be disposed by the appropriate means.
Immediately report any abnormalities to Toshiba Customer Support Center or an authorized representative.
8.2

UPS Clearance

Maintain the indicated clearance during installation. See Figure 8.1. Ensure that the front and top air vents are NOT blocked.
NOTE: Minimum front clearance for unobstructed airflow is 20 inches. However, minimum front clearance when physically
accessing the UPS must be at least the width of the front door of the UPS, or per NEC 110.34(A)(36 i n./900 mm) and local
requirements, whichever is greater.
26
Side Clearance
15-80kVA: 0 in (0 mm)
FIGURE 8.1: CLEARANCE FOR UPS USING LEVELING FEET
Top 16 in
(406 mm)
Front
36 in
(900 mm)
Back Clearance
15-80kVA: 0 in (0 mm)
4400 Series Installation and Operation Manual – 64527-008