4.2 System Pre-Installation

4.2.1 Site Selection
The AMPS HP systems are designed to be installed in a controlled environment, sheltered from rain, excessive
dust and other contaminants.
Consider both the floor loading and the physical space required for the power system and the batteries.
4.2.2 Floor Plan Layout
Sufficient free space must be provided at the front and rear of the power system to meet the cooling requirements
of the inverters and rectifiers(if installed) in the power system and to allow easy access to the power system com-
ponents.
Consider the following before selecting a location for the HP power system
Structure of building able to support the additional weight
Enough space to meet requirements for access
Enough space to meet cooling requirements of the rectifiers
Adequate space to do the install
Route that equipment will take through the building to reach the site
Check and record distances to load
Check and record distances to AC power source
Check and record distances to batteries/DC power source
Understand the full load on the DC system
Window for working hours and other similar restrictions
Work done in advance
x
Reinforce floors
x
Install distribution panels
Install cable racks
x
Run wiring
x
0260080-J0 Rev D
21

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AMPS HP2 Power System and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents