ATTACHMENTS, OPTIONS

DOZING WORK

DOZING ON LEVEL GROUND, OR DOWNHILL
NATURAL GROUND, BEDROCK
If you feel that the situation is dangerous when dumping the soil, for safety reasons, use 2 movements to push the soil over the
edge.
1. Dig with FORWARD PITCH (1), and when the load on the blade is approximately 80%, return to STRAIGHT
PITCH (2) and continue digging (A).
2. Set to REAR PITCH (3) which gives a larger load, and haul the soil (B).
Adjust the cutting angle to the most effective angle for rolling the soil.
3. Use FORWARD PITCH (1) to dump the soil (C).
FILLING, SOFT SOIL
Perform digging in R pitch or S pitch, and haul in R pitch.
REMARK
If the digging is performed in R pitch, there is no sudden digging
into the soil, and the operation can be performed smoothly.
EFFECTIVE METHOD OF OPERATION FOR DUAL TILTDOZER
WARNING
6 - 15