ATTACHMENTS, OPTIONS

EFFECTIVE METHOD OF OPERATION FOR DUAL TILTDOZER

BLADE CONDITION

SINGLE TILT
Operate single/dual tilt selector switch to SINGLE position, then
operate the tilt.
Applicable operation
Normal operations
DUAL TILT
Operate single/dual tilt selector switch to DUAL position, then
operate the tilt.
Applicable operation
Side cutting operations (high places)
Horizontal dozing operations form side slope (rough ground)
Ditching work
R PITCH (PITCH BACK)
Keep the pitch button pushed in and operate the left tilt.
Applicable operation
Hauling
Dozing soft soil (filling)
Leveling operations (spreading)
Side-cutting operations
EFFECTIVE METHOD OF OPERATION FOR DUAL TILTDOZER
6 - 13