144 Safe torque off function

Start-up including acceptance test

To ensure the safe operation of a safety function, validation is required. The final
assembler of the machine must validate the function by performing an acceptance
test. The acceptance test must be performed
• at initial start-up of the safety function
• after any changes related to the safety function (circuit boards, wiring,
components, settings, etc.)
• after any maintenance work related to the safety function.

Competence

The acceptance test of the safety function must be carried out by a competent person
with adequate expertise and knowledge of the safety function as well as functional
safety, as required by IEC 61508-1 clause 6. The test procedures and report must be
documented and signed by this person.

Acceptance test reports

Signed acceptance test reports must be stored in the logbook of the machine. The
report shall include documentation of start-up activities and test results, references to
failure reports and resolution of failures. Any new acceptance tests performed due to
changes or maintenance shall be logged into the logbook.