Mechanical installation

Refer to
To install a side option

Electrical installation

Connect the auxiliary voltage supply to the +24V and DGND terminals on the drive.
Refer to
Auxiliary voltage connection
connections to provide back-up power to the control board (I/O, fieldbus).

Start-up

To configure the BAPO module:
1. Power up the drive.
2. Set the parameter 95.04 Control board supply to 1 (External 24V).
BAPO-01 power extension module 179
on page 76.
on page 74. The BAPO module has internal