Chapter 4
Installation Procedure
Section 4.4
Cat5 Cable Requirements
All Cat5 cables used in the installation of the base station must meet the following requirements:
• Must be provided or approved by Siemens
• Must not be longer than 80 m (262 ft)
• Must be ground as shown in
Figure 9: Cat5 Cable Grounded
Section 4.5
Mounting Bracket Installation
The following procedures describe how to secure the mounting bracket to the CPE unit.
Procedure: Securing the Mounting Bracket to the Antenna
1.
Place the antenna/enclosure base bracket against the back of the antenna. Make sure it is oriented with the
elevation axis.
22
Figure 9
RUGGEDCOM WiN5100/WiN5200
Solder
Cat5 Cable Requirements
User Guide