Figure 97. Installing the PDB bridge board
e. Install the power distribution board bridge board.
f. Connect all the other cables to PDB 2.
Route these cables properly through the tabs on the chassis to prevent them from being pinched or crimped.
2.
Install PDB 1
a. Lower the PDB 1 such that the slot at the bottom of PDB 1 inserts into the PDB bridge board on PDB 2.
When the slot at the bottom of PDB 1 inserts into the PDB bridge board on PDB 2, the screw holes align with the holes on
the chassis.
b. Insert the screws that secure PDB 1 to the system.
c. Secure the power cables to PDB 1 by using screws.
d. Install the power cable cover for PDB 1 and secure it with the screw.
e. Connect all the cables to PDB 1.
Route these cables properly through the tabs on the chassis to prevent them from being pinched or crimped.