Preparing the Site

This section describes the steps you should take to prepare the site for your system.
"Cautions and Considerations" on page 95
"Reviewing System Specifications" on page 96
"Reviewing Power Requirements" on page 99
"Preparing for Cooling" on page 106
"Preparing the Unloading Route and Unpacking Area" on page 111
"Preparing the Network" on page 113

Cautions and Considerations

Consider the following when selecting a location for the new rack.
Do not install the rack in a location that is exposed to:
Use power outlets that provide proper grounding.
Observe the precautions, warnings, and notes about handling that appear on labels on the
equipment.
Direct sunlight
Excessive dust
Corrosive gases
Air with high salt concentrations
Frequent vibrations
Sources of strong radio frequency interference
Static electricity
A qualified electrical engineer must perform any grounding work.
Each grounding wire for the rack must be used only for the rack.
The grounding resistance must not be greater than 10 ohms.
Verify the grounding method for the building.