Completing The Test; Local Acceleration Logic Zclcpsch; Verifying The Settings - ABB Relion 670 Series REL670 Commissioning Manual

Line distance protection 2.1 iec
Table of Contents

Advertisement

Section 10
Testing functionality by secondary injection
10.11.3.3
10.11.4
10.11.4.1
216
Table 34:
Phase L1-N parameter values
Phase
I (Amps)
L1
0
L2
0
L3
0
If wanted, change all settings cyclically for other faults (L2-N and L3-N).
The setting parameter WEI is set to Echo & Trip.
1.
Apply input signals according Table 34.
2.
Activate the receive (CR) signal.
3.
After the IED has operated, turn off the input signals.
4.
Check that trip, send signal, and indication are obtained.
The ECHO output gives only a 200 ms pulse.

Completing the test

Continue to test another function or end the test by changing the TestMode setting to
Off. Restore connections and settings to their original values, if they were changed for
testing purposes.

Local acceleration logic ZCLCPSCH

Prepare the IED for verification of settings outlined in section
verify
settings".
The logic is checked during the secondary injection test of the impedance measuring
zones.

Verifying the settings

1.
Provide the IED with conditions equivalent to normal load for at least two
seconds.
2.
Deactivate the conditions for accelerated function.
3.
Apply a phase-to-earth fault at 100% of line impedance.
4.
Check that the fault is tripped with the second zone time delay.
5.
Provide the IED with conditions equivalent to normal load for at least two
seconds.
Phase-angle (Deg) V (Volts)
0
Set less than
240
63
120
63
Line distance protection REL670 2.1 IEC
1MRK 506 355-UEN A
Phase-angle (Deg)
UPN<
0
240
120
"Preparing the IED to
Commissioning manual